Xinjiang Runjust Project Planning of Phase I

Detailed progress description of the Phase I project plan

  1. Project feasibility study January 2021-March 2021
  2. Investment Agreement April 2021
  3. Registered capital in place April 2021
  4. Geological Survey and Design May 2021-October 2021
  5. Land use rights certificates May 2021
  6. EIA, Safety Assessment and Energy Assessment Approval May 2021 – July 2021
  7. Planning permission, certificate of commencement July 2021
  8. Procurement of equipment May 2021-October 2021
  9. Plant building construction July 2021-April 2022
  10. Equipment installation May 2022-August 2022
  11. #1 commissioning, stabilization September 2022 – October 2022
  12. #2 commissioning, stabilization October 2022 – November 2022

High Performance Carbon Fiber

If you want comprehensive information about carbon fiber production.

DROP US A LINE

If you are interested in our products, or want to consult related issues, please feel free to contact us, we will arrange experts to contact you.

Our Partners